24 Chapter 3 Preparing for installation
Step
Description
Check
2
Unpack the server, and ensure you have all the items you need (see
"Unpacking the 1005r server" (page 25)).
Complete the following checklists that are provided in the Installation
and Configuration Task List (NN44200-306):
• "CallPilot software media and documentation checklist"
•
"CallPilot server hardware checklist"
3
Remove the front bezel and inspect the front panel (see pages
"Removing the front bezel" (page 27)).
4
Place the 1005r server in the chosen location (see "Installing the
server" (page 29)).
5
Replace the front bezel (see page "To replace the front bezel" (page
30)).
Connect the 1005r server and devices as follows:
• Connect the monitor, keyboard, and mouse (see "Connecting
peripherals to the server" (page 31)).
•
Connect the modem (see "To connect the modem to the server"
(page 33)).
•
Connect the 1005r server to the ELAN Ethernet switch or hub
(Meridian 1 or CS 1000 only) (see "Connecting the server to the
ELAN subnet" (page 35)).
ATTENTION
To comply with EMC radiation requirements, a Class A Ethernet
switch or hub must be located 10 m (33 ft.) away from the 1005r
server. Shielded Ethernet cables must be used.
Note: If you are connecting the optional Nortel server subnet, do not
power up unless your antivirus programs and Nortel security updates
are installed first.
•
Connect the 1005r server to the Nortel server subnet Ethernet
switch or hub (optional) (see "Connecting the server to the Nortel
server subnet (optional)" (page 36)).
ATTENTION
To comply with EMC radiation requirements, a Class A Ethernet
switch or hub must be located 10 m (33 ft.) away from the 1005r
server. Shielded Ethernet cables must be used.
6
Nortel CallPilot
1005r Server Hardware Installation
NN44200-308 01.06 Standard
5.0 15 May 2008
Copyright © 2006-2008, Nortel Networks
.
Kommentare zu diesen Handbüchern